SPIRAL2 final commissioning results
Résumé
The commissioning of SPIRAL2 was carried out in different steps and slots from 2014 to end 2021. In a first phase, the proton-deuteron and heavy ion sources, LEBT lines and RFQ were commissioned and validated with A/Q=1 up to 3 particles. The validation of the MEBT (between the RFQ and the linac, including the Single Bunch Selector), linac and HEBT lines (up to the beam dump and to the NFS experimental room) started on July 2019, when GANIL received the authorization to operate SPIRAL2. The linac tuning is now validated with H⁺, 4He2+ and D⁺ and nominal H⁺ and D⁺ beams were sent to NFS for physics experiments. The main results obtained during the commissioning stages and the strategy used by the commissioning team are presented.