Article Dans Une Revue IAEE Energy Forum Année : 2020

Stranded assets risk derails Vietnam's plan for new coal power plants

Résumé

In 2016, Vietnam planned to build a fleet of new coal-fired power plants, expanding capacity to 54.5 GW in 2030, from 13.1 GW in 2015. Three years later, the risk of stranded assets not only made this plan sub-optimal, it also made it infeasible because investors are looking elsewhere.
Fichier principal
Vignette du fichier
main.pdf (149.92 Ko) Télécharger le fichier
main.odt (74.09 Ko) Télécharger le fichier
Origine : Fichiers produits par l'(les) auteur(s)

Dates et versions

halshs-02263622 , version 1 (05-08-2019)

Identifiants

  • HAL Id : halshs-02263622 , version 1

Citer

Minh Ha-Duong. Stranded assets risk derails Vietnam's plan for new coal power plants. IAEE Energy Forum, 2020, 102, pp.27-29. ⟨halshs-02263622⟩
180 Consultations
367 Téléchargements

Partager

Gmail Facebook X LinkedIn More